What to Do If Builder Delays Possession in Pune

Legal & Documentation
20 Aug 2025
blog post image

Introduction

Purchasing your dream house, whether it be in Wakad, Hinjewadi, or Kharadi in Pune, is a huge emotional and financial hurdle to overcome. But what if the builder is delaying possession? This is a serious concern in areas of Pune such as Hadapsar, Magarpatta, Baner, and Bavdhan where the demand is strong but the projects are long in delivery.

Delayed possession goes beyond being an inconvenience; it can creatively damage your finances by forcing you to pay both rent and EMIs. Luckily, you are not powerless. You can still draw on the protections of Pune real estate rules and regulations whether you are a novice homebuyer or an investor.

This guide by Property Aaj will cover your rights, how to deal with the builder, as well as the legal processes you can initiate to obtain your possession or reasonable or monetary compensation.


Why Do Builders Delay Possession in Pune?

Understanding the reasons can help you evaluate the situation better:

  • Regulatory delays (RERA or environmental approvals)

  • Shortage of funds or poor planning

  • Pandemic and labor issues

  • Land disputes or legal issues

  • Intentional delay for price speculation

While some reasons are genuine, many delays are avoidable and unfair to buyers.


What Are Your Rights as a Buyer in Pune?

Thanks to RERA (Real Estate Regulation and Development Act, 2016), you now have several rights:

  • Right to timely possession as per the agreement

  • Right to interest compensation for delays

  • Right to withdraw and get refund + interest

  • Righ to approach MahaRERA authority for justice

  • Right to lodge a consumer complaint

These rights apply to all RERA-registered projects. Most builders in Pune, especially in places like Kharadi, Wakad, and PCMC, are now RERA-compliant.


Steps to Take if Builder Delays Possession in Pune

Let’s look at a step-by-step approach:


1. Review Your Agreement for Possession Date

The Builder-Buyer Agreement clearly states:

  • The expected date of possession

  • Grace period (usually 6 months)

  • Force majeure clauses (natural disasters, etc.)

If the delay exceeds both the possession date and grace period, you can initiate action.


2. Communicate with the Builder First

Start with a formal written communication:

  • Ask for revised timeline in writing

  • Request reasons for delay

  • Keep email and letter records

Sometimes, delays are temporary and developers may offer compensation, free maintenance, or GST waivers to retain buyers.


3. Demand Compensation Under RERA

As per MahaRERA rules:

  • Builders must pay interest for every month of delay, calculated at SBI’s highest Marginal Cost of Lending Rate (MCLR) + 2%

  • You can file a complaint online at https://maharera.mahaonline.gov.in

  • It costs ₹5,000 to file a RERA complaint in Maharashtra

Documents Needed:

  • Builder-Buyer Agreement

  • Receipts of payments made

  • Correspondence history

  • Proof of delay


4. Opt for Withdrawal and Full Refund

If the delay is long and uncertain, you can cancel the agreement and ask for:

  • 100% refund of amount paid

  • Interest on the amount until refund is made

This right is available under Section 18 of RERA.

Many buyers in Magarpatta, Hadapsar, and Wagholi have successfully withdrawn and reinvested in ready-to-move homes through support from Property Aaj experts.


5. File Complaint in Consumer Forum

If you want to claim additional damages like:

  • Rent paid during delay

  • Mental harassment

  • Legal costs

You can file a complaint at:

  • District Consumer Disputes Redressal Commission (DCDRC) in Pune

  • Or use the E-Daakhil platform: https://edaakhil.nic.in

Consumer courts have awarded high compensation to buyers in Pune under the Consumer Protection Act, 2019.


6. Approach MahaRERA Adjudicating Officer for Fast Relief

If your claim is straightforward—interest on delay or refund—you may get faster resolution by:

  • Filing with MahaRERA Adjudicating Officer

  • Presenting your documents and oral statement

Hearings are usually conducted online or at the MahaRERA Pune office.


7. Check if Other Buyers Are Also Affected

Often, entire towers or phases are delayed. Consider:

  • Forming a buyers’ group

  • Filing a joint complaint

  • Negotiating compensation as a collective

In areas like Pimple Saudagar and Kharadi, buyers’ associations have helped fast-track project completion and refunds.


8. Check Project Status on MahaRERA Portal

Visit https://maharera.mahaonline.gov.in

  • Search by RERA number or project name

  • See if builder has updated construction status

  • Check if extensions or violations have been reported

If the builder hasn’t uploaded progress reports, it strengthens your complaint.


9. Engage a Real Estate Lawyer in Pune

If you’re unsure how to proceed, consult a property lawyer to:

  • Draft notices

  • File RERA or court complaints

  • Represent you at hearings

Property Aaj can connect you with verified legal professionals in Pune who specialize in delay-related cases.


10. Explore Alternative Properties

While fighting your case, also explore:

  • Ready-to-move homes in nearby areas

  • RERA-registered pre-launch projects with strong delivery history

  • Reputed developers in Baner, Bavdhan, or Wakad

Use Property Aaj's listings to find reliable, track-record-backed properties in Pune.


Compensation You’re Entitled To

Delay Type

Buyer’s Rights

Delay beyond possession date

Interest (RERA guidelines)

Builder offers no possession

Option to withdraw + refund + interest

Mental harassment or false promises

Damages through Consumer Forum

Possession with defects

Rectification under RERA


What If Builder Goes Insolvent or Abandons the Project?

This is rare but not impossible.

Steps:

  • File a claim through MahaRERA’s conciliation forum

  • If the builder is declared bankrupt, filed under Insolvency and Bankruptcy Code (IBC)

  • Join buyers' group to negotiate with administrator

The state government may also reassign the project to another developer under Resolution Plan


How Property Aaj Can Help

At Property Aaj, we understand the emotional toll a possession delay causes. That’s why we offer:

  • Legal consultation referrals

  • Verified project listings with timely delivery

  • Guides on RERA complaints

  • Updates on builder reputations in Pune

Whether you're stuck with an under-construction flat in Hinjewadi Phase 2 or waiting on a possession letter in Kothrud, we’re here to guide you through the process.


Conclusion

Purchasing a home is a life goal—and you deserve to be able to access it on time. If you are experiencing a delay with your possession in Pune, do not be afraid to speak up. To do this start with reviewing your agreement, followed by a formal inquiry and then assert your rights through RERA and Consumer Law.

Keep in mind, the law is now on your side and with platforms like MahaRERA, you can take action by getting what is just and what is fair or just your money back.

Be informed, be proactive, and most importantly always use trusted places like Property Aaj for safe and verified property transactions in Pune.


FAQs

1. What is the interest I can obtain if my flat is delayed in Pune?  

According to MahaRERA, you are entitled to interest calculated at the rate of the highest SBI MCLR + 2% per month for the period of delay.  

2. Can I get my money back if the builder delays possession?  

Yes. If the builder delays possession beyond the period agreed upon, you can cancel the booking and get a full refund along with interest as long as you proceed under RERA.

3. How much time will a RERA complaint take to resolve in Pune?  

Most complaints can take anywhere from 90–180 days; however, the resolution may take longer depending on the complexity and the response of the builder.

4. What if the builder’s project does not have RERA?  

All projects over 500 sq.m. or 8 apartments must register as per RERA. The failure of the builder to record with RERA as required makes them liable for breaching the law and subject to penalty.

5. Can I file a complaint with RERA and a consumer complaint?  

Yes. You can file the complaint with RERA for possession/interest, and also file a consumer complaint - for additional damages.

6. Can NRIs complain for possession delay?  

Yes, absolutely. NRIs can file a complaint with RERA online. They can also authorize someone in India through a Power of attorney to represent them.

Read more about property matters with our specialists and browse the latest property listings on Property Aaj. Download the app from the Play Store and App Store now for easy buying, selling, and renting!